How to make correct DC connections to the Manager Alpha

Due to the Manager Alpha’s ability to provide high constant current it is extremely important to ensure the DC connections are up to the task.

This information outlines the correct connection method for peak reliability and performance and explains what not to do when installing the Manager Alpha products.

Under no circumstances should cables be inserted into the end of the terminal and fastened with the top mounted screws as this will impact the performance and operation of the Manager.

CORRECT CONNECTION METHOD

Remove the bolts from the top of the terminal block and connect the cables to their corresponding terminals on the side of the Main Unit using the removed bolts. Secure and torque to 4.0 – 5.0 N·m (3.0 – 3.7 lbf·ft).

Cables must be connected to the main unit with lugged terminals. Do not use a rattle gun or impact driver to secure.

INCORRECT CONNECTION METHOD

CAUTION: DO NOT use the top facing terminals, doing so may strain and damage the cables. The top facing terminals also provide less contact area for the lugs, impacting the performance and operation of the Manager.